Tea estates / plantations · 2025

Estate Factory Backup, Nuwara Eliya

Nuwara Eliya

Estate Factory Backup, Nuwara Eliya
Array
22 kW
Bank
60 kWh
Inverter
20 kW
Commissioned
2025

The Problem

Grid interruptions during the plucking season were stalling withering lofts mid-cycle, and a stalled loft costs a whole day's leaf.

What We Built

A 22 kW roof and terrace array across two factory blocks, a 60 kWh bank in a purpose-built ventilated room, and 20 kW of hybrid inversion split across critical and non-critical boards.

The Result

Withering and rolling now ride through every dropout. The estate reports no leaf loss to power failure across two full seasons.

Racking / bank detail
Commissioning

Bill of Materials

Array38 × 580 W
Bank12 × 5 kWh @ 48 V
Inverter2 × 10 kW parallel
MountingRoof rail + terrace frame
MonitoringPer-string telemetry